Question 27

The stakeholders have indicated to the business analysis team that the documented requirements are ready for use in subsequent business analysis or implementation efforts. What type of requirements has been developed at this point in time?
  • A Approved
  • B Maintained
  • C Verified
  • D Validated
Reveal correct answer

Correct answer: A

Explanation

Approved requirements are those that stakeholders have agreed upon and are ready to be used in further business analysis or implementation efforts.