Your project implementation plan defines 12 capabilities of the planned systems solution that will not be needed once the new solution is operational. What type of requirements are these?
  • A Transition requirements
  • B Nonfunctional requirements
  • C Reusable requirements
  • D Functional requirements
Reveal correct answer

Correct answer: A

Explanation

Transition requirements describe the capabilities needed to transition from the current state to the future state. They are temporary and not needed once the transition is complete.