Question 78

Who has the best knowledge and skills to estimate how much work can be done in a Sprint?

(choose the best answer)

  • A Subject matter experts
  • B The Developers
  • C The Scrum Team
  • D The Product Owner
Reveal correct answer

Correct answer: B

Explanation

According to the Scrum Guide, the Developers are accountable for estimating the effort needed to create a usable Increment that meets the Definition of Done. They are the ones who have the best insight into the complexity and feasibility of the work. The Product Owner, the Scrum Team, and the subject matter experts are not involved in sizing the work.