Question 79

What is the duration of the gap between the conclusion of one Sprint and the commencement of the next Sprint?

(choose the best answer)

  • A There's a one-week hiatus after a four-week Sprint, and typically shorter for briefer Sprints.
  • B Just enough time to define and document the necessities for the upcoming Sprint.
  • C A duration required for the Developers to wrap up the testing from the preceding Sprint.
  • D Zero. A new Sprint starts immediately following the end of the previous Sprint.
  • E Any of the listed options might be valid, contingent on the context.
Reveal correct answer

Correct answer: D

Explanation

In Scrum, there is no downtime between Sprints. As soon as one Sprint ends, the next Sprint begins immediately. This ensures a continuous flow of development and maximizes the efficiency and productivity of the Scrum Team.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need