Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 69
True or False: The Scrum Master reports to the Product Owner.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
The Scrum Master and the Product Owner are peers with different responsibilities. Neither reports to the other.Discussion