Question 56
True or False: The Sprint for all the Scrum Teams working on the same product must start and end on the same date.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
Scrum does not require having aligned Sprints for multiple teams. The Scrum Teams self-manage and define the best option for them.Discussion