Professional Scrum Product Owner I PSPO I · Free Practice Question Medium
Question 43
True or False: If a Developer is disturbing and slowing down the Scrum Team, the Scrum Master is the only person responsible for addressing the issue.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
While the Scrum Master plays an important role in facilitating and coaching the team, resolving such issues is a collective responsibility of the entire Scrum Team. It is crucial for the team to work together, with the Scrum Master taking the lead, to identify the problem, find solutions, and improve team dynamics and productivity. Self-management and shared accountability are key principles in Scrum, requiring all team members to actively address challenges and foster a collaborative environment.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.