Professional Scrum Product Owner I PSPO I · Free Practice Question Easy

Question 44

True or False: The Product Owner is responsible to ensure that a sufficient number of Product Backlog items are chosen during the Sprint Planning event to meet stakeholder expectations.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

While the Product Owner collaborates with stakeholders to refine and prioritize the Product Backlog, the decision of how many items to select for the Sprint is made by the Developers during Sprint Planning based on their capacity and the Sprint Goal.