Professional Scrum Product Owner I PSPO I · Free Practice Question Easy

Question 42

Who is accountable for managing the Product Backlog?

(choose the best answer)

  • A The Developers
  • B The Scrum Master
  • C The Key Stakeholders
  • D The Product Owner
Reveal correct answer

Correct answer: D

Explanation

The Product Owner is accountable for effective Product Backlog management.