Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 41
Who holds the accountability for ordering the Product Backlog?
(choose the best answer)
- A The Product Owner and the Developers
- B The Developers
- C The Product Owner and the customer
- D The Product Owner
- E The Product Owner, the customer, and the Developers
Reveal correct answer
Correct answer: D
Explanation
According to Scrum, the Product Owner is solely accountable for ordering and prioritizing the items in the Product Backlog based on their value and needs of the stakeholders.Discussion