Question 29

True or False: The individuals external to the Scrum Team can participate in Sprint Planning to offer technical or domain expertise.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: A

Explanation

Sprint Planning is an opportunity to collaborate and ensure a shared understanding of what needs to be accomplished in the Sprint. While the core participants are the Developers and the Product Owner, input from external individuals can be valuable for making informed decisions.