Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 30
True or False: The Product Owner is accountable for maximizing the product's value.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: A
Explanation
This is true as per the Scrum Guide. The Product Owner is accountable for ensuring that the developed product delivers the maximum value.Discussion