Question 19

What should be the length of a Sprint?

(choose the best two answers)

  • A At least, one week
  • B Whatever works best for management
  • C Short enough to keep the business risks acceptable
  • D At most, one month
Reveal correct answers

Correct answers: C, D

Explanation

The Sprints are fixed length events of one month or less to create consistency. When a Sprint’s horizon is too long the Sprint Goal may become invalid, complexity may rise, and risk may increase. Shorter Sprints can be employed to generate more learning cycles and limit the risk of cost and effort to a smaller time frame.