Question 20
During the Sprint, who makes the decisions about the approach and techniques to carry out the tasks?
(choose the best answer)
- A The Developers
- B The Scrum Team
- C The Agile Coach
- D The Scrum Master
- E Technical experts
Reveal correct answer
Correct answer: A
Explanation
According to the Scrum Guide, Developers are responsible for how they turn Product Backlog items into Increments of potentially releasable product functionality. This means that they decide the technical approach, tasks, and activities necessary during the Sprint to produce the intended Increment. While the Scrum Master supports the team and the Product Owner represents the product's value and priorities, it's the Developers who actually determine how the work will be done during the Sprint.Discussion