Professional Scrum Product Owner Iii PSPO Iii · Free Practice Question Easy
Question 5
Part of the Sprint Review is for the stakeholders to re-prioritize items in the Product Backlog.
True or False :
- A True
- B False
Reveal correct answer
Correct answer: B
Explanation
The Sprint Review is an opportunity for the Scrum Team and stakeholders to inspect the Increment and adapt the Product Backlog if needed. However, the Product Backlog items and their prioritization are the responsibility of the Product Owner, not the stakeholders. The stakeholders may provide feedback and input, but the Product Owner makes the final decisions on the Product Backlog.Discussion