Question 91

In Scrum, when should a new Increment be available for inspection?

(choose the best answer)

  • A Before each planned release
  • B By the end of each Sprint, before the Sprint Review
  • C Every 2 Sprints
  • D Whenever the user acceptance testing is complete
  • E When the Scrum Master or the Product Owner asks for it
Reveal correct answer

Correct answer: B

Explanation

According to Scrum, a new Increment of the product must be available by the end of each Sprint, before the Sprint Review. This allows stakeholders to inspect the product's progress and provide feedback.