Professional Scrum Product Owner I PSPO I · Free Practice Question Easy

Question 9

Although they may vary with the domain of work, Product Backlog items often have the following attributes:

I - Size

II - Order

III - Description

(choose all that apply)

  • A I and II
  • B I and III
  • C II and III
  • D I, II and III
Reveal correct answers

Correct answer: D

Explanation

The correct answers are I) Size, II) Order, and III) Description. While attributes may vary depending on the context, these are common attributes of Product Backlog items that facilitate effective prioritization and planning.