Professional Scrum Product Owner I PSPO I · Free Practice Question Medium
Question 67
True or False: During Sprint Retrospective the definition of Done can not be reviewed and adapted.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
The Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done.Discussion