Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 64
True or False: The first Sprint can start as soon as the Product Backlog is complete.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
The Product Backlog is never complete. It's always evolving in adaptive methods.Discussion