Professional Scrum Product Owner I PSPO I · Free Practice Question Medium
Question 58
Which of the following are true regarding the Definition of Done?
(choose the best three answers)
- A Each Product Backlog item contains a Definition of Done containing the criteria it needs to meet to be accepted
- B Guides the Developers on how many Product Backlog items to select for the Sprint
- C Is committed to by the Increment
- D Defines the criteria for a Sprint to be Done
- E Increases transparency
Reveal correct answers
Correct answers: B, C, E
Explanation
"Each Product Backlog item contains ..."
- The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product.
"Guides the Developers on how ..."
- It is one of the factors used by the Developers during Sprint Planning to define what can be Done during the given Sprint.
"Is committed to by the Increment"
- The Increment commits to the Definition of Done.
"Defines the criteria for a Sprint to be Done"
- It defines when a Product Backlog item becomes an Increment.
"Increases transparency"
- The Definition of Done creates transparency by providing everyone a shared understanding of what work was completed as part of the Increment.