Professional Scrum Product Owner I PSPO I · Free Practice Question Medium

Question 58

Which of the following are true regarding the Definition of Done?

(choose the best three answers)

  • A Each Product Backlog item contains a Definition of Done containing the criteria it needs to meet to be accepted
  • B Guides the Developers on how many Product Backlog items to select for the Sprint
  • C Is committed to by the Increment
  • D Defines the criteria for a Sprint to be Done
  • E Increases transparency
Reveal correct answers

Correct answers: B, C, E

Explanation

"Each Product Backlog item contains ..."

- The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product.


"Guides the Developers on how ..."

- It is one of the factors used by the Developers during Sprint Planning to define what can be Done during the given Sprint.


"Is committed to by the Increment"

- The Increment commits to the Definition of Done.


"Defines the criteria for a Sprint to be Done"

- It defines when a Product Backlog item becomes an Increment.


"Increases transparency"

- The Definition of Done creates transparency by providing everyone a shared understanding of what work was completed as part of the Increment.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need