Question 47
You're tasked with guiding the creation of a new application involving seven Scrum Teams new to the framework. With an initial Product Backlog in place, what's the most effective strategy to reduce inter-team dependencies?
(choose the best answer)
- A Collaborate with the Developers to evaluate and break down the tasks.
- B Assign a unique Product Backlog to each Scrum Team.
- C Recognize the dependencies and rearrange the Product Backlog for six of the Product Owners.
- D Discuss this challenge with the Scrum Master as a potential obstacle.
- E Distribute Product Backlog tasks among the seven Product Owners.
Reveal correct answer
Correct answer: A
Explanation
When multiple Scrum Teams are working on the same product, ensuring minimal dependencies between the teams is crucial for smooth progress and delivering valuable increments. According to the Scrum Guide, the best approach would involve collaborating with Developers to analyze the work, understand the complexities, and find ways to minimize inter-team dependencies. While other options might sound logical, they don't directly address the minimization of dependencies and can cause more complexity.Discussion