Professional Scrum Master Ii PSM Ii · Free Practice Question Medium
Question 8
After several Sprints, a key stakeholder starts using the product. The stakeholders are surprised by the slow performance and complain to the Product Owner. The Product Owner comes to the Scrum Master asking for advice.What is the best course of action for a Scrum Master? (Choose the best answer)
- A Bring the concern to the testers and ask them to include performance testing.
- B Explain to the Product Owner that it’s up to the Developers to decide on acceptable performance standards as they own the Definition of Done.
- C Encourage the Product Owner to bring any performance issues to the Developers' attention and collaborate with them on how to improve performance and, as a result, have a stronger Definition of Done.
- D Wait until the next Sprint Retrospective to change the Definition of Done because that is when it is most appropriate.
Reveal correct answer
Correct answer: C
Explanation
The highest priority of agility is to satisfy the customer by delivering valuable software early and frequently. Developers can expand their Definition of Done to include more stringent criteria for higher quality because they are the ones doing the work and Increments must meet performance standards.Discussion