Professional Scrum Master Ii PSM Ii · Free Practice Question Medium

Question 2

Which statement is correct regarding the length of the Sprints? (Choose the best two answers)
  • A The Sprint Length is defined by the Scrum Master.
  • B The Sprint length depends on the forecasted development effort (amount of items selected) during Sprint Planning.
  • C The Sprint length is calculated by aggregating the time required to design, code and test.
  • D The length of all Sprints must be no more than one month and it is optimal to have a consistent Sprint length.
  • E If the duration of the Sprint extends beyond a certain point, it could lead to an increase in complexity, and a higher level of risk for the project or product.
Reveal correct answers

Correct answers: D, E

Explanation

Sprints are time-boxed events, meaning they have a fixed duration. While they are typically one month or less, they should be long enough to allow the Scrum Team to deliver a potentially releasable Increment of product. The guide also emphasizes that a new Sprint starts immediately after the conclusion of the previous Sprint, ensuring a consistent rhythm and pace for the team's work. If the duration of the Sprint extends beyond a certain point, it could lead to various challenges. These include the potential invalidation of the Sprint Goal, an increase in complexity, and a higher level of risk for the project or product.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need