Professional Scrum Master Ii PSM Ii · Free Practice Question Hard
Question 17
Five new Scrum teams are being formed by a company to work on a single product. Several future team members inquire about the Scrum Master's role in coordinating work among the various Scrum teams. What should the Scrum Master do next? (Choose the best answer)
- A Visit the five Scrum teams daily to ensure alignment and that all Sprint Backlogs remain synchronized.
- B Teach the Product Owner to collaborate with the technical leads to order the Product Backlog in such a way that there is no technical or development overlap during a Sprint.
- C Advise the teams to minimize dependencies by working on separate development branches and integrating at the end of four Sprint cycles.
- D Teach them that it is their responsibility to form the teams such that each team will have the necessary skills, knowledge, and competencies to create an integrated Increment by the end of every Sprint.
- E At the end of Sprint Planning, collect all Sprint tasks and create a consolidated plan for the entire Sprint.
Reveal correct answer
Correct answer: D
Explanation
In Scrum, teams are self-organizing and responsible for coordinating their own work. The Scrum Master's role is to empower and support the teams in organizing themselves effectively. Therefore, the Scrum Master should teach the teams that it's their responsibility to form teams with the necessary skills and competencies to deliver integrated Increments by the end of each Sprint. The Scrum Master should guide them in understanding the principles of self-organisation and encourage collaboration among teams.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.