Professional Scrum Master I PSM I · Free Practice Question Easy
Question 85
True or False: According to the Scrum framework, the Scrum components and rules for the project are chosen depending on the project's specific characteristics.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
While implementing only parts of Scrum is possible, the result is not Scrum. Scrum exists only in its entirety and functions well as a container for other techniques, methodologies, and practices.Discussion