Professional Scrum Master I PSM I · Free Practice Question Easy
Question 83
Which statement best describes the Sprint Backlog resulting from the Sprint Planning?
(choose the best answer)
- A Contains tasks lasting at most one day
- B It contains Product Backlog items selected by the Product Owner
- C It contains all the work to be delivered during the Sprint
- D It is the Scrum Team's plan for the Sprint
- E Every task has a designated owner
Reveal correct answer
Correct answer: D
Explanation
The output of the Sprint Planning is the first version of the Sprint Backlog, created by the collaborative work of the entire Scrum Team.Discussion