Professional Scrum Master I PSM I · Free Practice Question Easy
Question 66
Who has the authority to cancel the Sprint?
(choose the best answer)
- A The Key Stakeholders
- B The Scrum Master
- C The Developers
- D The Product Owner
- E The Product Owner and the Scrum Master
Reveal correct answer
Correct answer: D
Explanation
Only the Product Owner has the authority to cancel the Sprint, although he or she may do so under influence from the stakeholders, the Developers, or the Scrum Master.Discussion