Professional Scrum Master I PSM I · Free Practice Question Easy

Question 51

What is true about the Sprint Retrospective?

(choose the best answer)

  • A The Scrum Team and stakeholders participate.
  • B It occurs before the Sprint Review.
  • C It's an opportunity for inspection and adaptation of the process used by the Scrum Team.
  • D It can be facilitated by the Scrum Master, Product Owner, or a designated facilitator.
Reveal correct answer

Correct answer: C

Explanation

The Sprint Retrospective is an essential event in Scrum where the Scrum Team inspects and adapts its processes. It provides an opportunity to reflect on the Sprint, identify strengths and weaknesses, and plan improvements. The Scrum Team collaboratively discusses what went well, what could be improved, and formulates actionable steps to enhance their effectiveness and efficiency. The Sprint Retrospective is timeboxed to a maximum of three hours for a one-month Sprint, but shorter timeboxes are recommended for shorter Sprints. The event occurs after the Sprint Review and involves the participation of the entire Scrum Team, including the Product Owner.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need