Professional Scrum Master I PSM I · Free Practice Question Medium

Question 3

True or False: The Sprint Review is the only opportunity to inspect and adapt the product Increment
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

According to the Scrum Guide, the goal of each Sprint is to deliver a "Done" Increment of the product. However, there may be instances where the team faces challenges or unforeseen circumstances that make it difficult to deliver a complete and usable Increment within the Sprint timebox. This can happen due to various reasons such as technical complexities, dependencies, or external factors. It is important for the Scrum Team to continuously improve and strive to achieve a "Done" Increment every Sprint, but it is possible that they may not always be able to accomplish this goal.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need