Professional Scrum Master I PSM I · Free Practice Question Easy
Question 108
True or False: Each of the three artifacts in Scrum contains a commitment to them
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: A
Explanation
According to the Scrum Guide, each of the three artifacts in Scrum (Product Backlog, Sprint Backlog, and Increment) contains a commitment to them. The commitments serve as a guideline or expectation that helps ensure the effectiveness of the artifact. For example, the Product Backlog contains the commitment to providing transparency, ordering, and optimizing the value of the items. The Sprint Backlog contains the commitment to achieving the Sprint Goal and updating the work remaining. The Increment contains the commitment to being a potentially releasable product.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.