Certified Scrummaster CSM · Free Practice Question Medium

Question 3

If a Scrum Team becomes too large, all of the following should be considered, except:

  • A

    They should consider reorganizing into multiple cohesive Scrum Teams.

  • B

    Multiple Scrum Teams should focus on the same product.

  • C

    Multiple Scrum Teams should have dedicated Product Owner and Product Backlog.

  • D

    Multiple Scrum Teams should share the same Product Goal, Product Backlog, and Product Owner.

Reveal correct answer

Correct answer: C

Explanation

If Scrum Teams become too large, they should consider reorganizing into multiple cohesive Scrum Teams, each focused on the same product. Therefore, they should share the same Product Goal, Product Backlog, and Product Owner.The Scrum Guide, Page 5

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.