The Sprint Backlog is owned by:

  • A

    The Project Manager

  • B

    The Product Owner

  • C

    The Scrum Master

  • D

    The Developers

Reveal correct answer

Correct answer: D

Explanation

The Sprint Goal is a commitment by the Developers The Scrum Guide, Page 11