SAFE Release Train Engineer RTE · Free Practice Question Easy

Question 22

Among the following PI Planning elements, which one fosters transparency and helps engage Business Owners and stakeholders in the planning process?
  • A Team Iteration plans
  • B ART planning board
  • C Draft objectives
  • D ROAMing Risks
Reveal correct answer

Correct answer: B

Explanation

It accurately describes a key element in SAFe (Scaled Agile Framework) called the "Agile Release Train (ART) planning board." The ART planning board is a physical or digital board used during the PI (Program Increment) planning event in SAFe. During the PI planning event, the ART planning board is used to visualize and manage the planning process. It provides transparency by displaying the work items, features, and dependencies that need to be addressed during the Program Increment. This visual representation helps engage Business Owners and stakeholders in the planning process by allowing them to see the overall plan, understand the priorities, and actively participate in discussions related to feature sequencing, scope, and dependencies. The ART planning board typically includes various planning artifacts, such as program and team backlogs, feature cards, dependencies, risks, and objectives. It serves as a central point for collaboration and decision-making during the planning event, enabling Business Owners and stakeholders to actively contribute to the planning process and align on the priorities and objectives for the upcoming Program Increment. The ART planning board creates transparency by visually representing the planning process and engages Business Owners and stakeholders by involving them in the decision-making and prioritization activities.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need