Question 16
At which stage of an Inspect and Adapt (I&A) Event are the variations between the planned business value and the actual business value presented?
- A PI System Demo
- B Retrospective
- C Quantitative and qualitative measurement
- D Problem-solving workshop
Reveal correct answer
Correct answer: C
Explanation
The Inspect and Adapt (I&A) Event consists of three parts:
PI System Demo
Quantitative and qualitative measurement
Retrospective and problem-solving workshop
In the second part, Teams collectively review any quantitative and qualitative metrics they have agreed to collect, then discuss the data and trends.
Each Team's planned and actual business value is rolled up to create the ART predictability measure.
Study Guide: Here's the SAFe 6.0 article with the complete explanation: https://scaledagileframework.com/inspect-and-adapt/