SAFE Product Ownerproduct Manager POPM · Free Practice Question Easy
Question 9
What is included in the Inspect and Adapt Agenda?
- A Quantitative and Qualitative measurement
- B Management Review and confidence vote
- C ART Backlog Refinement
- D None
Reveal correct answer
Correct answer: A
Explanation
The Inspect and Adapt (I&A) Event consists of three parts:
PI System Demo
Quantitative and qualitative measurement
Retrospective and problem-solving workshop
Study Guide: Here's the Scaled Agile SAFe 6.0 article with the complete explanation: https://scaledagileframework.com/inspect-and-adapt/