SAFE Product Ownerproduct Manager POPM · Free Practice Question Easy
Question 24
What is the intended value of the Team Sync event?
-
A
The team aligns on the progress of Iteration Goals
-
B
The team is able to commit to a set of goals to be delivered in the Iteration
-
C
The team reviews and improves processes before the next Iteration
-
D
The team is able to prepare requirements for Iteration Planning
Reveal correct answer
Correct answer: A
Explanation
As we've seen in the previous exams : The Team Sync is a short, daily meeting where the team comes together to review their progress towards their Iteration Goals, identify any roadblocks, and make a plan for the next day. It is an opportunity for the team to communicate and collaborate, and to ensure that they are all working towards the same goals.
After the Team Sync, if the team identify any areas where they can improve their process. For example, if the team is struggling to meet their Iteration Goals, they may use the "meet after" board during Team Sync to to write it down and talk about it after the team sync to brainstorm ways to improve their efficiency or to reduce the number of rework items.