Which of the following is NOT a reason to use a predictive life cycle?
  • A The solution cannot be completely designed before it is developed.
  • B Formal approvals and checkpoints are required.
  • C A high level of risk is involved.
  • D A structured project management process will be used.
Reveal correct answer

Correct answer: A

Explanation

A predictive life cycle is generally used when the work involves a high level of risk and will be formally managed. If a solution cannot be completely designed upfront, it may be built in short iterations, and requirements reprioritized as the solution is developed.