PMI Professional In Business Analysis PMI Pba · Free Practice Question Medium
Question 38
Which of the following are ALL components of a requirements management plan?
- A Work packages, requirements packages, workflow management process, and a release plan
- B Solution requirements, stakeholder matrix, requirements deliverables, and an implementation management process
- C Traceability structure, configuration management, and a requirements prioritization process
- D Vision document, project scope statement, requirements estimates, and a vendor management process
Reveal correct answer
Correct answer: C
Explanation
A requirements management plan describes how requirements will be analyzed, documented, and managed, including which requirements will be traced and how that will be accomplished, and a requirements prioritization processDiscussion