PMI Professional In Business Analysis PMI Pba · Free Practice Question Medium

Question 38

Which of the following are ALL components of a requirements management plan?
  • A Work packages, requirements packages, workflow management process, and a release plan
  • B Solution requirements, stakeholder matrix, requirements deliverables, and an implementation management process
  • C Traceability structure, configuration management, and a requirements prioritization process
  • D Vision document, project scope statement, requirements estimates, and a vendor management process
Reveal correct answer

Correct answer: C

Explanation

A requirements management plan describes how requirements will be analyzed, documented, and managed, including which requirements will be traced and how that will be accomplished, and a requirements prioritization process

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need