PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy

Question 32

Which of the following is the BEST approach to managing project changes?
  • A Have the sponsor approve all changes.
  • B Discover changes as early as possible.
  • C Create a scope diagram with very clear boundaries.
  • D Prevent changes that affect the project scope.
Reveal correct answer

Correct answer: B

Explanation

Some project changes, including scope or cost changes, will add value to the project, and therefore should not be eliminated unilaterally. The sponsor is not involved in all changes. Changes found early will have less of an impact on the project. Thus, it is best to discover needed changes as early as possible.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.