PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy

Question 30

One of your stakeholders prefers daily contact and another prefers only to be involved when he asks for information. How do you decide on the frequency of communications with stakeholders?
  • A Work with your project manager to balance the needs as much as possible.
  • B Ask your project manager for the required reporting cycle.
  • C Ask your sponsor how often he or she wants you to communicate to the team.
  • D Communicate whenever a significant change in requirements is identified.
Reveal correct answer

Correct answer: A

Explanation

Stakeholders' communications preferences vary, so the business analyst and project manager need to balance the needs. With a large group of stakeholders, it may not be possible to tailor communications for each preference, so a compromise may be needed. If there is a significant change in requirements, the change control process is managed and communicated by the project manager.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need