PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy

Question 21

A couple of months after your project is complete, you go out to the business stakeholders' location to check on their operations. The purpose of this visit is:
  • A Post-implementation assessment
  • B Observation
  • C Lessons learned
  • D Project closing
Reveal correct answer

Correct answer: A

Explanation

You may use observation to see how things are going, but your purpose is to evaluate how well the solution is working and meeting the original project goals. You may get some lessons learned while you are there, but your focus is on measuring the performance of the transition and implementation of the solution.