Question 10

The business analyst determines that a change is needed to material that has been purchased for the project. The business analyst calls a meeting of the team to plan how to make the change. This is an example of:
  • A Lack of a clear work breakdown structure.
  • B Lack of a change management plan.
  • C Management by objectives.
  • D Good team relations.
Reveal correct answer

Correct answer: B

Explanation

The business analyst is asking how to make a change. The procedures, forms, sign-offs, and other similar requirements for handling changes should have already been determined in the change management plan.