Rye’s team has just completed their fifth iteration on Project Looking Glass. They have worked to continuously tweak the look and feel of the user interface of their product since the first iteration. These changes over time are a good example of:
  • A A waste to the project
  • B Critical experience and design
  • C The Agile UI method
  • D Incremental product improvement
Reveal correct answer

Correct answer: D

Explanation

These changes are incremental product improvements. This is an example of how a product can change and adjust over time to new information or requirements.The Agile UI method and critical experience and design are fictional terms in this scenario. Constantly improving the product is not necessarily a waste to the process.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.