PMI Agile Certified Practitioner PMI ACP · Free Practice Question Medium
Question 7
Dylan completes one on one coaching activities with his team. When he learns that Berkeley has a concern, he brings her concern up to the team in their next daily standup. His Agile mentor tells him that:
- A This was not appropriate, as the daily standup should not involve discussion of roadblocks
- B This was appropriate, as the best thing to do is always to bring issues up to the team
- C This was not appropriate, as one on one coaching should be kept confidential
- D This was appropriate, as Dylan knows a couple of other team members have a similar issue
Reveal correct answer
Correct answer: C
Explanation
One on one coaching conversations should always be kept confidential, where people feel safe sharing the information.The other answers are not the most prudent in this scenario. This was not appropriate because one-on-one coaching is confidential. It should not be shared with the team.Discussion