PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 58

Brody has recently been assigned the task of creating an Agile PMO for the Cincinnati, Ohio, office of Willis Enterprises. Which of the following characteristics will not be part of creating this new Agile PMO?
  • A Multidisciplinary
  • B Invitation-oriented
  • C Value-driven
  • D Isolated
Reveal correct answer

Correct answer: D

Explanation

Isolated is the correct answer. An Agile Project Management Office (PMO) cannot be isolated because Agile methodology emphasizes collaboration, communication, and transparency across all project stakeholders, including the PMO. The Agile PMO serves as a critical link between the project team and the organization's senior management, ensuring that the project aligns with the organization's strategic goals, objectives, and values. In an Agile environment, the PMO is not a separate entity but is integrated into the project team, serving as a facilitator and enabler of Agile practices. The PMO provides support, guidance, and coaching to the project team on Agile principles, practices, and tools. It also ensures that the project is following the organization's standards, policies, and procedures.Value-driven, Invitation-oriented, and multidisciplinary are key characteristics of an Agile PMO.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need