PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 56

Jon is working with his product owner to help determine a rough order of magnitude estimate for upcoming user stories early on in their planning process. What is Jon most likely doing?
  • A Sizing user stories
  • B Decomposing user stories
  • C Estimating user stories
  • D Planning user stories
Reveal correct answer

Correct answer: A

Explanation

Jon is sizing user stories before a more detailed estimate is produced later. T-shirt sizing focuses on a high-level estimate that might give a general idea of the size of an item.True estimates will be more accurate and produced closer to the work being done. This type of estimation does not refer to planning or decomposing user stories.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need