PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 44

You are a developer working on an Agile project. Your entire team has been asked by the Agile team leader to submit cycle time for the next three iterations. What does the leader mean by cycle time?
  • A The time that is between each iteration for review and feedback
  • B The time it takes to complete each iteration from start to finish
  • C The time it will take to complete all three iterations
  • D The time it takes to figure out what is in the iteration
Reveal correct answer

Correct answer: B

Explanation

Cycle time is the time it takes to complete an iteration from start to finish. Cycle time is a subset of lead time, which determines the time it will take to do the entire project.The other responses are incorrect. Cycle time doesn’t address the required time to determine what’s in the iteration, the duration of the iterations, or the timeboxed ceremonies between iterations.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need