Robert, a senior project manager who works for a computer company, has been assigned a project to design a new laptop model for an area where the company is looking to expand its market share. The requirements, some new materials, and specific technological gadgets have never been created or used in any previous or current models. What is the best approach to take for Robert to ensure project success?
  • A Kanban
  • B Lean
  • C Agile approach
  • D Traditional predictive approach
Reveal correct answer

Correct answer: C

Explanation

Robert is involved in a project to deliver a new type of product never built before by the company with a high level of uncertainty. When dealing with a high level of uncertainty, it is best to use an Agile project management approach which allows for flexibility, collaboration, and focus on continuous improvement, making it well-suited for navigating uncertain and complex environments.Because this project has a high level of uncertainty in the work to be carried out, the traditional predictive approach is not the best approach in this situation. Lean, Kanban, are Agile approaches to execute the project, but these all fall under the Agile approach umbrella, so the correct answer is an Agile approach.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need