PMI Agile Certified Practitioner PMI ACP · Free Practice Question Medium

Question 37

A team is working on an Agile project, and the product owner notices that the team is taking longer than usual to complete their work. She decides to use the seven wastes concept to identify the cause and eliminate the problem. Which of the following is NOT one of the seven wastes in Agile project management?
  • A Waiting
  • B Overprocessing
  • C Multitasking
  • D Defects
Reveal correct answer

Correct answer: C

Explanation

The correct answer is multitasking. By focusing on eliminating waste, teams can optimize their processes and increase efficiency. The seven wastes in Agile project management are overproduction, overprocessing, waiting, excess inventory, unnecessary motion, defects, and unused talent.Multitasking is not one of the wastes listed. Agile teams often limit multitasking as it can reduce productivity and increase the risk of errors.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need