PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 27

Of the following trends, which are expected in agile development?
  • A The decrease in risk occurs faster than in traditional development
  • B Over time, adaptability increases
  • C Over time, visibility increases in a linear way
  • D At the conclusion of the project, business value experiences a significant increase
Reveal correct answer

Correct answer: A

Explanation

The correct answer is that risk decreases more quickly than in traditional development. Over the course of an agile project, risk decreases rather steadily. The other responses are incorrect because until a project is finished, traditional projects experience little decrease in risk; the achievement of business value should occur as early in the project as possible; agile projects should demonstrate visibility and adaptability from start to finish; value should show a steady increase with increments.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need